What Is a Door Schedule and Why Is It Important for Quotation?

What a door schedule does

A commercial door schedule is the shared reference that connects every opening to its required leaf, frame, finish, hardware and performance. It normally uses a unique door mark for each type or opening. Suppliers use those marks to calculate quantities, identify missing details and prepare a quotation that can be checked against the drawings.

Core information to include

  • Door mark, quantity, location and room references.
  • Leaf width, height, thickness, material and finish.
  • Frame profile, depth, material and wall condition.
  • Required rating, vision panel, louver and seals.
  • Handing and the corresponding hardware set.

When some information is not finalized, mark it clearly instead of leaving an unexplained blank. This helps suppliers separate confirmed scope from allowances.

Why schedules improve quotation accuracy

Without a structured schedule, suppliers may count openings differently or assume standard frames, finishes and hardware. The resulting prices cannot be compared fairly. A schedule makes exclusions visible and allows revisions to be tracked by door mark. It also supports the quotation process described in the fire door quotation checklist.

Coordinate drawings and hardware

Check the schedule against floor plans, elevations and life-safety drawings. Hardware sets should match handing, access control and exit requirements. The door hardware preparation guide explains the machining and reinforcement details that should be connected to each mark.

Control revisions before production

Add a revision number and date, highlight changed openings and issue one approved schedule with the shop drawings. Changes to ratings, sizes, frames or hardware after production begins may affect both cost and delivery. Keep a record of supplier questions and approved answers.

What to send with the schedule

Include plans, elevations, specifications, hardware information, finish references, destination and required delivery dates. If the schedule is incomplete, submit the available documents through the project quotation form so missing fields can be identified before pricing.